Delays on July 13th, 2017
Latest alerts
- July 13th, 2017 at 9:59pm
- The Princeton Shuttle (Dinky) will be temporarily suspended as of 10:52 pm due to operational issues. Substitute bus service is being provided.
- July 13th, 2017 at 8:30pm
- M&E train #0441 the 8:04pm from Stirling is up to 25 min. late due to congestion late train ahead.
- July 13th, 2017 at 8:11pm
- M&E train #0439 the 7:29pm from Gillette is up to 25 min. late due late train ahead.
- July 13th, 2017 at 8:04pm
- M&E train #6663, the 7:51pm from Newark Broad St. is up to 10 min. late due to congestion.
- July 13th, 2017 at 7:58pm
- NEC train #3963, the 7:49pm from New Brunswick, is up to 15 min. late due to an earlier mechanical problem.
- July 13th, 2017 at 7:52pm
- M&E train #6437, the 7:19pm from Basking Ridge is up to 20 min. late due to operational issues.
- July 13th, 2017 at 7:47pm
- M&E train #6670, the 7:31pm from Chatham is up to 10 min. late due to operational issues.
- July 13th, 2017 at 7:42pm
- Northeast Corridor
- NJCL train #3441, the 6:51pm from PSNY, is CANCELLED due to a mechanical problem. Customers to train #3283, the 8:22pm from PSNY.
- July 13th, 2017 at 7:42pm
- M&E train #0882 the 7:17pm is up to 25 min. late due to congestion late train ahead.
- July 13th, 2017 at 7:34pm
- Hudson-Bergen Light Rail
- MBPJ train #1225 the 7:15pm from Ho-Ho-Kus is up to 15 min. late due to train ahead.
- July 13th, 2017 at 7:33pm
- M&E train #6668, the 7:12pm from Milburn is up to 20 min. late due to operational issues.
- July 13th, 2017 at 7:27pm
- Hudson-Bergen Light Rail
- MBPJ train #0059 the 6:25pm from Secaucus is up to 15 min. late due to congestion.
- July 13th, 2017 at 7:21pm
- Northeast Corridor
- Update: NJCL train #3441, the 6:51pm from PSNY, is now 30 min. delayed due to an operational issue and a mechanical problem. Update to follow.
- July 13th, 2017 at 7:14pm
- Hudson-Bergen Light Rail
- MBPJ train #1173 the 6:59pm from Wesmont is up to 15 min. late due to train ahead.
- July 13th, 2017 at 7:10pm
- M&E train #6653, the 6:23pm from Maplewood is up to 45 min. late due to congestion from late trains ahead.
- July 13th, 2017 at 7:09pm
- BetMGM Meadowlands Rail Line
- MOBO train #1055, the 6:40pm from Mount Arlington is up to 30 min. late due to an earlier fallen tree across the tracks.
- July 13th, 2017 at 7:03pm
- Newark Light Rail
- PVL train #1635, the 6:45pm from Essex Street is up to 20 min. late due to operational issues.
- July 13th, 2017 at 6:59pm
- Northeast Corridor
- NJCL train #3441, the 6:51pm from PSNY, is delayed due to an operational issue. Update to follow.
- July 13th, 2017 at 6:55pm
- M&E train #0858 the 6:20pm from Dover is up to 35 min. late due earlier fallen tree across tracks.
- July 13th, 2017 at 6:39pm
- Hudson-Bergen Light Rail
- MBPJ train #0057, the 6:23pm from Ramsey RT 17 is up to 30 min. late due to operational issues.
- July 13th, 2017 at 6:38pm
- M&E train #0332 the 6:12pm from Summit up to 15 min. late due to congestion.
- July 13th, 2017 at 6:32pm
- M&E train #0880, the 6:13pm from Millburn is up to 20 min. late due to congestion from a late train ahead.
- July 13th, 2017 at 6:30pm
- Newark Light Rail
- PVL train #1633 the 6:06pm from Secaucus is up to 20 min. late due to operational issues.
- July 13th, 2017 at 6:25pm
- Hudson-Bergen Light Rail
- MBPJ train #1271, the 6:02pm from Hoboken is up to 25 min. late due to earlier operational issues.
- July 13th, 2017 at 6:22pm
- Update: NEC #train #3866, the 5:52pm from Rahway, is now operating 30 min. late due to earlier police activity on train #3266 ahead.
- July 13th, 2017 at 6:21pm
- Northeast Corridor
- Update: NJCL train #3266, the 5:43pm from Rahway, is now operating 35 min.late due to earlier police activity.
- July 13th, 2017 at 6:19pm
- Hudson-Bergen Light Rail
- MBPJ train #0055, the 6:04pm from Sloatsburg is up to 15 min. late due to mechanical problems.
- July 13th, 2017 at 6:16pm
- M&E train #6431, the 5:43pm from Newark Broad St is up to 30 min. late due to earlier operational issues.
- July 13th, 2017 at 6:03pm
- Hudson-Bergen Light Rail
- MBPJ train #1274 the 5:46pm from Radburn is up 10 min. late due to train ahead.
- July 13th, 2017 at 6:00pm
- NEC train #3866, the 5:52pm from Rahway, is delayed due to police activity on train #3266 ahead. Update to follow.
- July 13th, 2017 at 5:57pm
- Northeast Corridor
- NJCL train #3266, the 5:43pm from Rahway, is delayed due to police activity. Update to follow.
- July 13th, 2017 at 5:48pm
- M&E train #6431, the 5:27pm from Hoboken is delayed in Hoboken due to operational issues. An update will follow.
- July 13th, 2017 at 5:47pm
- Hudson-Bergen Light Rail
- MBPJ train #0053 the 5:41pm from Tuxedo is up to 10 min. late due to congestion.
- July 13th, 2017 at 5:36pm
- M&E train #0660 the 5:23pm from East Orange is up to 10 min. late due to congestion.
- July 13th, 2017 at 5:36pm
- M&E train #6664, the 5:15pm from Dover is up to 15 min. late due to operational issues.
- July 13th, 2017 at 5:29pm
- M&E train #6643, the 4:47pm from Hoboken is up to 35 min. late due to earlier operational issues.
- July 13th, 2017 at 5:20pm
- M&E train #6643, the 4:47pm from Hoboken is delayed due to operational issues. An update will follow.
- July 13th, 2017 at 5:13pm
- Hudson-Bergen Light Rail
- MBPJ train #1122 the 4:56pm from Suffern is delayed due to disabled train ahead. An update will follow.
- July 13th, 2017 at 5:09pm
- NEC train #3864, the 4:44pm from Trenton, is up to 15 min. late due to an earlier mechanical problem.
- July 13th, 2017 at 4:55pm
- Hudson-Bergen Light Rail
- MBPJ train #0051, the 4:48pm from Suffern is up to 15 min. late due to a disabled train ahead.
- July 13th, 2017 at 4:54pm
- Hudson-Bergen Light Rail
- MBPJ Line train #0066 the 4:23pm from Ramsey Rt.17 is up to 25 min. late due to accommodating customers from an earlier cancelled train.
- July 13th, 2017 at 4:52pm
- Hudson-Bergen Light Rail
- MBPJ train #1178, the 4:30pm from Mahwah is up to 15 min. late due to accommodating customers from an earlier cancelled train.
- July 13th, 2017 at 4:41pm
- M&E train #6656 the 3:44pm from Dover is CANCELLED due to operational issues. Customers may use train #6658 the 4:07pm from Denville.
- July 13th, 2017 at 4:41pm
- M&E train #6658, the 4:07pm from Denville is up to 30 min. late due to earlier mechanical problems.
- July 13th, 2017 at 4:10pm
- Hudson-Bergen Light Rail
- MBPJ train #1120, the 4:06pm from Suffern is CANCELLED due to an operational issue. Customers may use trains #66 and #1178 from Suffern.
- July 13th, 2017 at 4:02pm
- Hudson-Bergen Light Rail
- MBPJ train #1113, the 3:52pm from Ramsey RT 17 is up to 10 min. late due to a late train ahead.
- July 13th, 2017 at 3:51pm
- Hudson-Bergen Light Rail
- MBPJ train #1159, the 3:35pm from Ramsey is up to 20 min. late due to accommodating customers from an earlier cancelled train.
- July 13th, 2017 at 3:44pm
- Hudson-Bergen Light Rail
- MBPJ train #0049, the 3:20pm from Ramsey RT 17 is CANCELLED due to mechanical problems. Customers may use train #1159 from Ramsey RT 17 making extra stops to Middletown.
- July 13th, 2017 at 3:31pm
- M&E train #6641, the 4:18pm from Hoboken is CANCELLED due to mechanical problems. Customer may use train #6341 the 4:09pm & train #0645 the 5:09pm from Hoboken.
- July 13th, 2017 at 2:26pm
- BetMGM Meadowlands Rail Line
- MOBO train #6245 the 2:09pm from Watchung Avenue is up to 10 min. late due to track maintenance.
- July 13th, 2017 at 1:21pm
- BetMGM Meadowlands Rail Line
- MOBO train #6241 the 1:04pm from Bay Street is up to 10 min. late due to track maintenance.
- July 13th, 2017 at 12:25pm
- NEC train #3840, the 12:06pm from Metuchen is up to 20 min. late, due to an earlier medical emergency.
- July 13th, 2017 at 12:00pm
- Hudson-Bergen Light Rail
- MBPJ train #1216, the 11:15am from Clifton is Cancelled due to a mechanical problem. Customers may use train #1116, the 12:34pm from Clifton.
- July 13th, 2017 at 11:32am
- Hudson-Bergen Light Rail
- MBPJ train #1216, the 11:15am from Clifton is delayed due to mechanical problems. An update will follow.
- July 13th, 2017 at 11:20am
- BetMGM Meadowlands Rail Line
- MOBO train #6233, the 11:04am from Bay Street is up to 20 min. late due to track maintenance.
- July 13th, 2017 at 11:17am
- BetMGM Meadowlands Rail Line
- MOBO train #6226, the 10:58am from Upper Montclair is up to 20 min. late due to track maintenance.
- July 13th, 2017 at 11:11am
- NEC train #3841, the 12:01pm from PSNY is CANCELLED, due to operational issues. Customer may use train #3843, the 12:37pm from PSNY.
- July 13th, 2017 at 10:35am
- BetMGM Meadowlands Rail Line
- MOBO train #6231, the 10:19am from Bay Street is up to 25 min. late due to track maintenance.
- July 13th, 2017 at 10:27am
- BetMGM Meadowlands Rail Line
- MOBO train #6222, the 10:19am from Bay Street is up to 15 min. late due to track maintenance.
- July 13th, 2017 at 10:06am
- NEC train #3832, the 9:48am from Metuchen is up to 15 min. late, due to an earlier mechanical problem.
- July 13th, 2017 at 7:56am
- NEC train #3936, the 9:21am from Trenton is CANCELLED, due to operational issues. Customers may use train #3834, the 9:52am from Trenton.
- July 13th, 2017 at 7:30am
- Hudson-Bergen Light Rail
- MBPJ train #0054, the 7:13am from Otisville is on the move and up to 25 min. late due to an earlier mechanical problem.
- July 13th, 2017 at 7:28am
- NEC train #3930, the 8:11am from Trenton is CANCELLED, due to operational issues. Customers may use train #3932, the 8:26am from Trenton.
- July 13th, 2017 at 7:26am
- NEC train #3126 the 8:12am from NPS is cancelled due to a mechanical problem. Customers to train #3712 the 8:16am from NPS.
- July 13th, 2017 at 7:17am
- Hudson-Bergen Light Rail
- MBPJ train #0054, the 7:13am from Otisville is disabled due to mechanical problems. Update to follow.
- July 13th, 2017 at 5:23am
- Newark Light Rail
- NJ TRANSIT summer rail schedule is in effect now through 9/1/17 to accommodate Amtrak track work at PSNY. Visit njtransit.com/theupdate
- July 13th, 2017 at 5:23am
- BetMGM Meadowlands Rail Line
- NJ TRANSIT summer rail schedule is in effect now through 9/1/17 to accommodate Amtrak track work at PSNY. Visit njtransit.com/theupdate
- July 13th, 2017 at 5:23am
- Hudson-Bergen Light Rail
- NJ TRANSIT summer rail schedule is in effect now through 9/1/17 to accommodate Amtrak track work at PSNY. Visit njtransit.com/theupdate
- July 13th, 2017 at 5:23am
- NJ TRANSIT summer rail schedule is in effect now through 9/1/17 to accommodate Amtrak track work at PSNY. Visit njtransit.com/theupdate
- July 13th, 2017 at 5:23am
- NJ TRANSIT summer rail schedule is in effect now through 9/1/17 to accommodate Amtrak track work at PSNY. Visit njtransit.com/theupdate
- July 13th, 2017 at 5:23am
- Northeast Corridor
- NJ TRANSIT summer rail schedule is in effect now through 9/1/17 to accommodate Amtrak track work at PSNY. Visit njtransit.com/theupdate
- July 13th, 2017 at 5:23am
- NJ TRANSIT summer rail schedule is in effect now through 9/1/17 to accommodate Amtrak track work at PSNY. Visit njtransit.com/theupdate