Delays on March 14th, 2017

Latest alerts

March 14th, 2017 at 9:06pm
Newark Light Rail
PVL train #2133 the 11:21pm from Hoboken is CANCELLED due to man power shortage. Customers to train #2101 the 12:45pm from Hoboken.
March 14th, 2017 at 8:20pm
Morris & Essex Line service is now operating on or close to schedule in both directions between Newark Broad Street and Millburn stations with some residual delays.
March 14th, 2017 at 8:10pm
M&E train #6941 the 9:11pm from NYPS is CANCELLED due to man power shortage. Customers to train #6943 the 10:11pm from NYPS.
March 14th, 2017 at 8:01pm
M&E train #6936 the 7:05pm from Dover is CANCELLED due to man power shortage. Customers to train #6938 the 8:03pm from Dover.
March 14th, 2017 at 7:45pm
UPDATE: M&E train #6937, the 7:11pm from NYPS is up to 30 min. late due to an operational issue.
March 14th, 2017 at 7:16pm
M&E train #6937, the 7:11pm from NYPS is delayed, due to an operational issue. An update will follow
March 14th, 2017 at 7:00pm
Newark Light Rail
PVL train #2123, the 6:21pm from Hoboken, is CANCELLED due to a manpower shortage. Customers to train #2125, the 7:29pm from Hoboken Making local stops.
March 14th, 2017 at 6:58pm
Newark Light Rail
UPDATE: PVL train #2125, the 7:29pm from Hoboken, WILL OPERATE tonight, making local stops.
March 14th, 2017 at 6:56pm
Newark Light Rail
Rail service will operate on a President's Day schedule Wednesday March 15, 2017. Service may operate west of Dover on the Morris & Essex Line and west of Bay Street on the Montclair Boonton Line. Trains do not operate from Jersey Avenue on the Northeast Corridor Line or west of Raritan and Lake H
March 14th, 2017 at 6:56pm
BetMGM Meadowlands Rail Line
Rail service will operate on a President's Day schedule Wednesday March 15, 2017. Service may operate west of Dover on the Morris & Essex Line and west of Bay Street on the Montclair Boonton Line. Trains do not operate from Jersey Avenue on the Northeast Corridor Line or west of Raritan and Lake H
March 14th, 2017 at 6:56pm
Hudson-Bergen Light Rail
Rail service will operate on a President's Day schedule Wednesday March 15, 2017. Service may operate west of Dover on the Morris & Essex Line and west of Bay Street on the Montclair Boonton Line. Trains do not operate from Jersey Avenue on the Northeast Corridor Line or west of Raritan and Lake H
March 14th, 2017 at 6:56pm
Rail service will operate on a President's Day schedule Wednesday March 15, 2017. Service may operate west of Dover on the Morris & Essex Line and west of Bay Street on the Montclair Boonton Line. Trains do not operate from Jersey Avenue on the Northeast Corridor Line or west of Raritan and Lake H
March 14th, 2017 at 6:56pm
Rail service will operate on a President's Day schedule Wednesday March 15, 2017. Service may operate west of Dover on the Morris & Essex Line and west of Bay Street on the Montclair Boonton Line. Trains do not operate from Jersey Avenue on the Northeast Corridor Line or west of Raritan and Lake H
March 14th, 2017 at 6:56pm
Northeast Corridor
Rail service will operate on a President's Day schedule Wednesday March 15, 2017. Service may operate west of Dover on the Morris & Essex Line and west of Bay Street on the Montclair Boonton Line. Trains do not operate from Jersey Avenue on the Northeast Corridor Line or west of Raritan and Lake H
March 14th, 2017 at 6:56pm
Rail service will operate on a President's Day schedule Wednesday March 15, 2017. Service may operate west of Dover on the Morris & Essex Line and west of Bay Street on the Montclair Boonton Line. Trains do not operate from Jersey Avenue on the Northeast Corridor Line or west of Raritan and Lake H
March 14th, 2017 at 6:52pm
Newark Light Rail
PVL train #2129, the 9:21pm from Hoboken, is CANCELLED due to a manpower shortage.
March 14th, 2017 at 6:52pm
Newark Light Rail
PVL train #2133, the 11:21pm from Hoboken, is CANCELLED due to a manpower shortage.
March 14th, 2017 at 6:51pm
Newark Light Rail
PVL train #2125, the 7:29pm from Hoboken, is CANCELLED due to a manpower shortage.
March 14th, 2017 at 6:49pm
Newark Light Rail
PVL train #2124, the 7:13pm from Spring Valley, is CANCELLED due to a manpower shortage. Customers to train #2126, the 8:11pm from Spring Valley.
March 14th, 2017 at 6:46pm
Newark Light Rail
UPDATE: PVL train #2122, the 6:06pm from Spring Valley, is CANCELLED due to a manpower shortage.
March 14th, 2017 at 6:23pm
M&E train #6932 the 5:42pm from Summit is up to 40 min. late due to a downed tree in the overhead wire near Mountain Station.
March 14th, 2017 at 6:22pm
Newark Light Rail
1 of 2: Rail service will operate on a President's Day schedule Wednesday 3/15/17. Service may operate west of Dover on the M&E and west of Bay St on the MOBO.
March 14th, 2017 at 6:22pm
BetMGM Meadowlands Rail Line
1 of 2: Rail service will operate on a President's Day schedule Wednesday 3/15/17. Service may operate west of Dover on the M&E and west of Bay St on the MOBO.
March 14th, 2017 at 6:22pm
Hudson-Bergen Light Rail
1 of 2: Rail service will operate on a President's Day schedule Wednesday 3/15/17. Service may operate west of Dover on the M&E and west of Bay St on the MOBO.
March 14th, 2017 at 6:22pm
1 of 2: Rail service will operate on a President's Day schedule Wednesday 3/15/17. Service may operate west of Dover on the M&E and west of Bay St on the MOBO.
March 14th, 2017 at 6:22pm
1 of 2: Rail service will operate on a President's Day schedule Wednesday 3/15/17. Service may operate west of Dover on the M&E and west of Bay St on the MOBO.
March 14th, 2017 at 6:22pm
Northeast Corridor
1 of 2: Rail service will operate on a President's Day schedule Wednesday 3/15/17. Service may operate west of Dover on the M&E and west of Bay St on the MOBO.
March 14th, 2017 at 6:22pm
1 of 2: Rail service will operate on a President's Day schedule Wednesday 3/15/17. Service may operate west of Dover on the M&E and west of Bay St on the MOBO.
March 14th, 2017 at 6:22pm
Update: M&E train #6929, the 3:31pm from NBS, is CANCELLED due to a downed tree in the overhead wire. Customers to train #6931, the 4:30pm from NBS.
March 14th, 2017 at 6:18pm
Newark Light Rail
PVL train #2122, the 6:06pm from Spring Valley, is delayed due to an operational issue. An update will follow.
March 14th, 2017 at 6:11pm
Morris & Essex Line service has resumed in both directions between Newark Broad Street and Millburn stations, using only one available track. Trains are now subject to up to 90 minute delays.
March 14th, 2017 at 6:07pm
UPDATE: M&E train #6931 the 4:36pm from East Orange is now up to 90 min. due to a downed tree in the overhead wire near Mountain Station.
March 14th, 2017 at 6:04pm
Atlantic City Rail Line
ACRL train #4633, the 5:36pm from Atco, is up to 25 min. late due to an earlier disabled Amtrak train.
March 14th, 2017 at 5:55pm
Hudson-Bergen Light Rail
MBPJ train #0079, the 6:13pm from Hoboken, is CANCELLED due to an operational issue. Customers to train #1729, the 6:25pm to Suffern.
March 14th, 2017 at 5:47pm
UPDATE: M&E train #6928, the 3:54pm from Maplewood is CANCELLED due to a downed tree in the overhead wire near Mountain Station.
March 14th, 2017 at 5:42pm
M&E train #6933, the 5:11pm from NYPS is CANCELLED, due to operational issues.
March 14th, 2017 at 5:33pm
Northeast Corridor
UPDATE: NJCL train #4753, the 4:46pm from Long Branch, is now operating up to 45 min. late due to a late connection.
March 14th, 2017 at 5:31pm
M&E Line service is STILL suspended between NBS and Millburn due to a downed tree in the overhead wires west of Mountain Station. No alternate svc is provided.
March 14th, 2017 at 5:28pm
M&E train #6933, the 5:11pm from NYPS is being delayed, due to operational issues. An update will follow.
March 14th, 2017 at 5:18pm
M&E train #6931 the 4:36pm from East Orange is delayed up to 45 min. due to a downed tree in the overhead wire near Mountain Station. An update will follow.
March 14th, 2017 at 5:10pm
Northeast Corridor
NJCL train #4753, the 4:46pm from Long Branch, is delayed due to a late connection. An update will follow.
March 14th, 2017 at 4:58pm
NEC train #7850, the 4:18pm from Trenton is up to 35 min. late, due to following a late train ahead.
March 14th, 2017 at 4:51pm
NEC train #7848, the 4:15pm from Princeton Jct., is up to 35 min. late, due to an earlier mechanical problem.
March 14th, 2017 at 4:48pm
NEC train #7846, the 4:20pm from EWR is up to 25 min late due to following late trains ahead.
March 14th, 2017 at 4:46pm
BetMGM Meadowlands Rail Line
MOBO train #0531 4:38pm from Watsessing Ave., is up to 15 min. late due to a late connection.
March 14th, 2017 at 4:30pm
M&E Line service is suspended between Newark Broad Street and Millburn due to a downed tree in the overhead wires. No alternate service is being provided.
March 14th, 2017 at 4:18pm
M&E train #6928, the 3:54pm from Maplewood is currently delayed due to a downed tree in the overhead wire near Mountain Station. An update will follow.
March 14th, 2017 at 4:16pm
M&E train #6929, the 3:51pm from Newark Broad St. is currently delayed due to a downed tree in the overhead wire near Mountain Station. An update will follow.
March 14th, 2017 at 4:00pm
Update: NEC train #7853, the 3:24pm from Secaucus, is now operating up to 30 min. late due to a switch problem ahead.
March 14th, 2017 at 3:56pm
Update: M&E train #6929, the 3:20 from Secaucus, is now operating up to 30 min. late due to a switch problem.
March 14th, 2017 at 3:47pm
All Morris & Essex Line train service is on hold at Mountain station due to a downed tree in the overhead wire. Trains 6928 and 6929 are the first affected.
March 14th, 2017 at 3:46pm
Northeast Corridor
NJCL train #7253, the 3:16pm from Secaucus, is up to 30 min. late due to an earlier delayed train.
March 14th, 2017 at 3:43pm
M&E train #6935 the 6:11pm from NYPS is CANCELLED due to man power shortage. Customers to train #6937 the 7:11pm from NYPS.
March 14th, 2017 at 3:42pm
NEC train #7853, the 3:24 from Secaucus, is delayed due to a switch problem ahead. Update to follow.
March 14th, 2017 at 3:42pm
M&E train #6930 the 4:05pm from Dover is CANCELLED due to man power shortage. Customers to train #6932 the 5:03pm from Dover.
March 14th, 2017 at 3:36pm
M&E train #6929, the 3:20 from Secaucus, is delayed due to a switch problem ahead. Update to follow.
March 14th, 2017 at 3:24pm
Newark Light Rail
PVL train #2117, the 3:29pm from Hoboken, is CANCELLED due to operational issues. Customers to train #2119, the 4:13pm from Hoboken.
March 14th, 2017 at 3:21pm
NEC train #7849 the 3:02pm from Metuchen is up to 20 min. late due an earlier switch problem.
March 14th, 2017 at 3:14pm
Hudson-Bergen Light Rail
MBPJ train #0075, the 3:09pm from Campbell Hall, is up to 10 min. late due to weather related conditions.
March 14th, 2017 at 3:07pm
Update: NEC train #7847, the 2:39pm from Metuchen, is now operating up to 25 min. late, due to an earlier switch problem.
March 14th, 2017 at 3:01pm
NEC train #7847, the 2:39pm from Metuchen, is delayed due to a switch failure ahead. An update will follow.
March 14th, 2017 at 2:55pm
Hudson-Bergen Light Rail
UPDATE: MBPJ train #1871 the 2:35pm from Rutherford is now up to 20 min. late due to an earlier switch problem.
March 14th, 2017 at 2:54pm
Hudson-Bergen Light Rail
MBPJ train #0078, the 3:05pm from Port Jervis, is CANCELLED due to an operational issue. Customers to train #0080 the 5:27pm from Port Jervis.
March 14th, 2017 at 2:23pm
Hudson-Bergen Light Rail
UPDATE 2: MBPJ train #0076, the 12:17pm from Ramsey, is now up to 2 hrs. late due to a mechanical problem.
March 14th, 2017 at 1:38pm
Northeast Corridor
NJCL train #7236, the 1:14pm from Little Silver, is up to 30 min. late due to weather related conditions.
March 14th, 2017 at 1:24pm
Hudson-Bergen Light Rail
UPDATE: MBPJ train #0073, the 1:25pm from Harriman is now operating up to 55 min. late due to an earlier delayed train ahead delayed train ahead.
March 14th, 2017 at 12:59pm
Hudson-Bergen Light Rail
MBPJ train #0073, the 1:25pm from Harriman is delayed due to a delayed train ahead. An update will follow.
March 14th, 2017 at 12:58pm
Hudson-Bergen Light Rail
Update: MBPJ Line train #0076 the 11:32am from Salisbury Mills is up to 90 min. late, due to a mechanical problem.
March 14th, 2017 at 12:47pm
Hudson-Bergen Light Rail
MBPJ train #0073, the 1:25pm from Harriman is up to 20 min. late due to a late train ahead.
March 14th, 2017 at 12:37pm
Northeast Corridor line trains are now operating on or close to schedule in both directions, with residual delays to trains already enroute.
March 14th, 2017 at 12:35pm
M&E Line train #6920 the 12:25pm from Secaucus is up to 15 min. late, due to weather related conditions.
March 14th, 2017 at 11:58am
Newark Light Rail
PVL train #2110, the 11:45am from Nanuet is up to 15 min. late due to a switch problem.
March 14th, 2017 at 11:51am
Northeast Corridor
NJCL train #7228, the 11:22am from Middletown is up to 25 min. late due to operational issues.
March 14th, 2017 at 11:42am
Hudson-Bergen Light Rail
Update: MBPJ train #1712, the 11:08am from Suffern is up to 35 min. late due to an earlier switch problem.
March 14th, 2017 at 11:26am
NEC train #7826 the 10:54am from Edison is up to 30 min. late, due to an Amtrak signal problem.
March 14th, 2017 at 11:23am
Hudson-Bergen Light Rail
MBPJ Line train #0076 the 11:02am from Otisville is up to 30 min. late, due to weather related issues.
March 14th, 2017 at 11:16am
Northeast Corridor
NJCL train #4729 the 11:01am from Bradley Beach is up to 15 min. late, held for an earlier delayed connection.
March 14th, 2017 at 11:14am
Hudson-Bergen Light Rail
MBPJ train #1712, the 11:08am from Suffern is delayed due to a switch problem. An update will follow.
March 14th, 2017 at 10:11am
NEC train #7820 the 9:34am from Edison is up to 35 min. late due to Amtrak signal problem.
March 14th, 2017 at 10:06am
NEC train #7825 the 9:26am from Princeton Junction is up to 40 min. late, due to an Amtrak signal problem.
March 14th, 2017 at 9:47am
Hudson-Bergen Light Rail
MBPJ Line train #0071 the 9:52am from Ridgewood is up to 10 min. late, due to an earlier mechanical problem.
March 14th, 2017 at 9:41am
Northeast Corridor trains are subject to 20 minute delays in both directions due to an Amtrak signal problem near Trenton station.
March 14th, 2017 at 9:30am
Northeast Corridor
NJCL train #7229, the 9:07am from NYPS is up to 20 min. late due to operational issues.
March 14th, 2017 at 9:27am
Northeast Corridor
NJCL train #7229, from NYPS is up to 20 min. late due to operational issues.
March 14th, 2017 at 9:24am
Hudson-Bergen Light Rail
MBPJ Line train #1708 the 9:08am from Suffern is up to 15 min. late, due to an earlier mechanical problem.
March 14th, 2017 at 9:18am
M&E Line train #6916 the 9:03am from Dover is up to 15 min. late, due to weather related conditions.
March 14th, 2017 at 9:00am
Hudson-Bergen Light Rail
Metro North rail service in/out of Grand Central will be suspended as of 12noon, however, NJ Transit will continue to operate Metro North's west of Hudson contract rail service from Port Jervis/Spring Valley to Hoboken on a weekend schedule.
March 14th, 2017 at 8:30am
Hudson-Bergen Light Rail
MBPJ Line train #0072 the 8:25am from Harriman is up to 10 min. late, due to weather related conditions.
March 14th, 2017 at 8:24am
Northeast Corridor
NJCL train #7216, the 8:12am from Little Silver is up to 15 min. late due to weather related conditions.
March 14th, 2017 at 7:42am
Northeast Corridor
Update: NJCL train #7212, the 7:06am from Long Branch is up to 30 min. late due to earlier mechanical problems.
March 14th, 2017 at 7:37am
Atlantic City Rail Line
ACRL train #4612, the 7:28am from Atco is up to 15 min. late due to weather related conditions.
March 14th, 2017 at 7:28am
Northeast Corridor
NJCL train #7217, the 7:13am from Matawan is up to 10 min. late due to operational issues.
March 14th, 2017 at 7:24am
Northeast Corridor
NJCL train #7212, the 7:06am from Long Branch is delayed due to mechanical problems. An update will follow.
March 14th, 2017 at 6:53am
Northeast Corridor
NJCL train #7208, the 6:42am from South Amboy is up to 15 min. late due to earlier operational issues.
March 14th, 2017 at 6:36am
Atlantic City Rail Line
Atlantic City Rail Line service will operate on a normal weekday schedule. Rail service will operate on a WEEKEND SCHEDULE today, March 14, 2017. System-wide cross honoring is in effect with light rail, PATH and ferry. NJ TRANSIT bus service is suspended for the day.
March 14th, 2017 at 6:36am
Newark Light Rail
Atlantic City Rail Line service will operate on a normal weekday schedule. Rail service will operate on a WEEKEND SCHEDULE today, March 14, 2017. System-wide cross honoring is in effect with light rail, PATH and ferry. NJ TRANSIT bus service is suspended for the day.
March 14th, 2017 at 6:36am
BetMGM Meadowlands Rail Line
Atlantic City Rail Line service will operate on a normal weekday schedule. Rail service will operate on a WEEKEND SCHEDULE today, March 14, 2017. System-wide cross honoring is in effect with light rail, PATH and ferry. NJ TRANSIT bus service is suspended for the day.
March 14th, 2017 at 6:36am
Hudson-Bergen Light Rail
Atlantic City Rail Line service will operate on a normal weekday schedule. Rail service will operate on a WEEKEND SCHEDULE today, March 14, 2017. System-wide cross honoring is in effect with light rail, PATH and ferry. NJ TRANSIT bus service is suspended for the day.
March 14th, 2017 at 6:36am
Atlantic City Rail Line service will operate on a normal weekday schedule. Rail service will operate on a WEEKEND SCHEDULE today, March 14, 2017. System-wide cross honoring is in effect with light rail, PATH and ferry. NJ TRANSIT bus service is suspended for the day.
March 14th, 2017 at 6:36am
Atlantic City Rail Line service will operate on a normal weekday schedule. Rail service will operate on a WEEKEND SCHEDULE today, March 14, 2017. System-wide cross honoring is in effect with light rail, PATH and ferry. NJ TRANSIT bus service is suspended for the day.