Delays on August 20th, 2019
Latest alerts
- August 20th, 2019 at 9:35pm
- NEC train #3880 the 9:22pm from Metro Park is up to 15 min. late due to striking a deer near Edison.
- August 20th, 2019 at 8:28pm
- Northeast Corridor
- NJCL train #4375, the 8:15pm from Bradley Beach, is up to 15 min. late held for an earlier connection at Long Branch.
- August 20th, 2019 at 7:47pm
- Newark Light Rail
- PVL train #1637 the 7:37pm from Westwood is up to 15 min. late due to an earlier mechanical problem.
- August 20th, 2019 at 7:33pm
- Northeast Corridor
- NJCL train #3275, the 7:25pm from Matawan, is up to 15 min. late due to earlier congestion from delayed trains ahead.
- August 20th, 2019 at 7:08pm
- Northeast Corridor
- NJCL train #3272, the 6:50pm from Middletown is up to 15 min. late due to a bridge strike near Red Bank.
- August 20th, 2019 at 6:52pm
- Northeast Corridor
- NJCL train #3515, the 6:43pm from EWR is up to 10 min. late due to congestion from a late train ahead.
- August 20th, 2019 at 6:45pm
- NEC train #3873, the 6:36pm from EWR is up to 10 min. late due to operational issues.
- August 20th, 2019 at 6:39pm
- Atlantic City Rail Line
- ACRL train #4635, the 6:23pm from Lindenwold, is up to 15 min. late due to earlier congestion from a delayed train ahead.
- August 20th, 2019 at 6:36pm
- Northeast Corridor
- NJCL train #3267, the 6:20pm from South Amboy, is up to 15 min. late due to heavy passenger travel.
- August 20th, 2019 at 5:52pm
- Northeast Corridor
- NJCL train #4367, the 7:09pm from Long Branch is cancelled due to a mechanical problem. Customers to train #3373 the 7:30pm from Long Branch.
- August 20th, 2019 at 5:44pm
- Northeast Corridor
- NJCL train #2609, the 5:45pm from Newark Penn Station is up to 10 min. late due to an equipment issue resulting from crew availability.
- August 20th, 2019 at 5:33pm
- M&E train #0645 the 5:18pm from Newark Broad St. is up to 20 min. late due to an earlier mechanical problem.
- August 20th, 2019 at 5:28pm
- M&E train #0645 the 5:18pm from Newark Broad St. is up to 15 min. late due to a mechanical problem. An update will follow.
- August 20th, 2019 at 5:21pm
- Northeast Corridor
- NJCL train #2605, the 5:10pm from South Amboy, is up to 10 min. late due to earlier congestion from a train ahead.
- August 20th, 2019 at 4:41pm
- Hudson-Bergen Light Rail
- MBPJ Line train #0061, the 6:27pm from Hoboken, is cancelled Tues. 8/20 due to equipment availability resulting from mechanical issues. Customers to train #0063 the 6:57pm from Hoboken.
- August 20th, 2019 at 4:39pm
- NEC train #3165, the 4:50pm from PSNY is cancelled Tuesday, 8/20 due to equipment availability resulting from mechanical issues. Customers to train #3511, the 5:01pm travelling to Rahway and #3725, the 5:08pm from PSNY to Jersey Ave.
- August 20th, 2019 at 4:39pm
- BetMGM Meadowlands Rail Line
- MOBO train #1009, the 5:50pm from Hoboken is cancelled Tuesday, 8/20 due to equipment availability. Customers to train #1011 the 6:33pm from Hoboken.
- August 20th, 2019 at 3:34pm
- M&E train #0428, the 3:15pm from Basking Ridge is up to 20 min. late due to an earlier equipment issue resulting from engineer availability.
- August 20th, 2019 at 3:08pm
- M&E train #0428, the 2:55pm from Gladstone is subject to a 30 min. delay due to an equipment issue resulting from engineer availability.
- August 20th, 2019 at 2:05pm
- RVL train #5725 the 1:52pm from Bound Brook is up to 15 min. late due to track maintenance.
- August 20th, 2019 at 1:36pm
- Atlantic City Rail Line
- ACRL train #4627, the 1:24pm from Cherry Hill, is up to 20 min. late due to a signal issue near Cherry Hill.
- August 20th, 2019 at 1:09pm
- Hudson-Bergen Light Rail
- MBPJ train #0062, the 12:57pm from Mahwah, is up to 15 min. late due to track maintenance.
- August 20th, 2019 at 1:02pm
- RVL train #5423, the 12:52pm from Bound Brook, is up to 15 min. late due to track maintenance.
- August 20th, 2019 at 12:49pm
- Hudson-Bergen Light Rail
- Update: MBPJ train #1153 the 12:15pm from Radburn is up to 30 min. late due to earlier mechanical problems.
- August 20th, 2019 at 12:31pm
- Hudson-Bergen Light Rail
- MBPJ train #1153 the 12:15pm from Radburn is up to 20 min. late due to mechanical problems.
- August 20th, 2019 at 12:09pm
- Hudson-Bergen Light Rail
- MBPJ train #0045, the 11:57am from Otisville, is up to 15 min. late due congestion from track maintenance.
- August 20th, 2019 at 12:06pm
- RVL train #5421, the 11:53am from Bridgewater, is up to 15 min. late due to track maintenance.
- August 20th, 2019 at 11:17am
- RVL train #5719, the 11:03am from Raritan, is up to 15 min. late due to track maintenance.
- August 20th, 2019 at 11:11am
- Atlantic City Rail Line
- ACRL train #4620, the 11:02am from Atco, is up to 20 min. late due to a signal problem.
- August 20th, 2019 at 10:32am
- Hudson-Bergen Light Rail
- MBPJ train #0043, the 10:27am from Otisville, is up to 10 min. late due to earlier congestion.
- August 20th, 2019 at 10:19am
- NEC train #3833, the 9:59am from PSNY is 15 min. late due to equipment availability.
- August 20th, 2019 at 9:41am
- M&E train #0626, the 9:30am from Newark Broad Street, is up to 15 min. late due to congestion resulting from late trains ahead.
- August 20th, 2019 at 9:38am
- RVL train #5415, the 9:27am from Westfield, is up to 15 min. late due to congestion resulting from track maintenance.
- August 20th, 2019 at 9:33am
- M&E train #6324, the 9:18am from Brick Church, is up to 15 min. late due to following late train #6624.
- August 20th, 2019 at 9:31am
- Atlantic City Rail Line
- ACRL train #4616 the 9:19am from Lindenwold is up to 15 min. late due to mechanical problems.
- August 20th, 2019 at 9:31am
- M&E train #6624, the 9:16am from Secaucus, is up to 25 min. late due to making additional stops for cancelled train #0808.
- August 20th, 2019 at 9:05am
- M&E train #0416, the 8:57am from Newark Broad Street, is up to 15 min. late due to making additional stops for cancelled train #808.
- August 20th, 2019 at 8:09am
- M&E train #0416, the 8:38am from Summit, will make additional stops today, 8/20 to accommodate customers from cancelled train #0808.
- August 20th, 2019 at 7:50am
- BetMGM Meadowlands Rail Line
- MOBO train #1006, the 7:30am from Dover, is up to 20 min. late due to accommodating customers from cancelled train #0808.
- August 20th, 2019 at 7:41am
- Hudson-Bergen Light Rail
- MBPJ train #1206, the 7:27am from Ridgewood, is up to 15 min. late due to equipment availability.
- August 20th, 2019 at 6:51am
- BetMGM Meadowlands Rail Line
- MOBO train #1006, the 7:20am from Lake Hopatcong, will depart Lake Hopatcong at 7:41am today 8/20 to accommodate customers from cancelled train #0808.
- August 20th, 2019 at 6:39am
- NEC train #3701, the 6:26am from New Brunswick is up to 20 min. late due to earlier crew member availability.
- August 20th, 2019 at 6:25am
- Hudson-Bergen Light Rail
- MBPJ train #1208 the 7:51am from Waldwick is cancelled Tuesday 8/20, due to engineer availability. Customers to train #1210 the 8:33am from Waldwick.
- August 20th, 2019 at 5:38am
- Hudson-Bergen Light Rail
- MBPJ train #0046, the 5:03am from Port Jervis is up to 25 min. late due to an earlier late train #41 ahead.
- August 20th, 2019 at 4:24am
- M&E train #0808, the 7:41am from Lake Hopatcong is cancelled due to equipment availability resulting from mechanical problems. Customers to train #1006 departing Lake Hopatcong at 7:41am and train #6624, the 8:08am from Dover making additional stops.
- August 20th, 2019 at 3:22am
- Hudson-Bergen Light Rail
- MBPJ train #0042, the 3:50am from Port Jervis is cancelled Tuesday, 8/20 due to equipment availability resulting from mechanical issues. Customers to train #0044 the 4:35am from Port Jervis.