Latest alerts
- May 18th, 2018 at 7:58pm
- M&E train #0441 the 7:38pm from Millburn is up to 20 min. late due to an operational issue.
- May 18th, 2018 at 7:36pm
- UPDATE: M&E train #6359 the 5:09pm from Newark Broad St. is now up to 25 min. late due to earlier police assistance.
- May 18th, 2018 at 7:21pm
- M&E train #6359 the 5:09pm from Newark Broad St. is up to 10 min. late due to police assistance. An update will follow.
- May 18th, 2018 at 6:50pm
- M&E train #0433 the 6:36pm from Millington is up to 15min. late due to a late train ahead.
- May 18th, 2018 at 6:45pm
- M&E train #6431 the 6:30pm from Lyons is up to 15min. late due to an operational issue.
- May 18th, 2018 at 6:18pm
- Atlantic City Rail Line
- UPDATE: ACRL train #4632 the 5:51pm from Pennsauken is now up to 20 min. late due to earlier Conrail Delair Bridge opening.
- May 18th, 2018 at 6:05pm
- Hudson-Bergen Light Rail
- MBPJ Line train #1167 the 5:48pm from Radburn is up to 20 min. late due to an operational issue.
- May 18th, 2018 at 6:04pm
- Atlantic City Rail Line
- ACRL train #4632 the 5:51pm from Pennsauken is up to 10 min. late due to Conrail Delair Bridge opening. An update will follow.
- May 18th, 2018 at 4:34pm
- NEC train #3896, the 4:18pm from Hamilton, is up to 15 min. late due to late train AM42 ahead.
- May 18th, 2018 at 3:58pm
- UPDATE: M&E train #6656 the 3:44pm from Dover is now up to 10 min. late due to an equipment issue.
- May 18th, 2018 at 3:53pm
- M&E train #6656 the 3:44pm from Dover is expected to be 20 min. late due to an equipment issue.
- May 18th, 2018 at 3:45pm
- UPDATE: M&E train #6654 the 3:20pm from Dover is now up to 20 min. late due to an earlier mechanical problem.
- May 18th, 2018 at 3:36pm
- Hudson-Bergen Light Rail
- MBPJ train #1269 the 5:27pm from Hoboken will not operate. Customers may use train #1167 departing Hoboken at 5:27pm today.
- May 18th, 2018 at 3:32pm
- M&E train #6654 the 3:20pm from Dover is up to 15 min. late due to a mechanical problem. An update will follow.
- May 18th, 2018 at 3:09pm
- NEC train #3852, the 2:58pm from Rahway, is up to 10 min. late due to late Amtrak train AM650 ahead.
- May 18th, 2018 at 2:12pm
- Northeast Corridor
- NJCL train #3243 the 2:00pm from Middletown is up to 15 min. late due to track maintenance.
- May 18th, 2018 at 1:36pm
- RVL train #5175, the 1:25pm from Cranford is up to 15 min. late due to track maintenance.
- May 18th, 2018 at 1:02pm
- Update 2: M&E train #6640, the 12:36pm from Summit is operating up to 25 min. late due to mechanical problems.
- May 18th, 2018 at 12:57pm
- Update: M&E train #6640, the 12:36pm from Summit is up to 20 min. delayed due to mechanical problems. An update will follow.
- May 18th, 2018 at 12:47pm
- Northeast Corridor
- NJCL train #3239, the 12:36pm from Perth Amboy is up to 10 min. late due to track maintenance.
- May 18th, 2018 at 12:43pm
- Northeast Corridor
- NJCL train #4335, the 12:30pm from Elberon is up to 10 min. late due to a late connection.
- May 18th, 2018 at 12:40pm
- M&E train #6640, the 12:26pm from Madison is up to 10 min. late due to earlier mechanical problems.
- May 18th, 2018 at 12:03pm
- Newark Light Rail
- Trains in and out of PSNY are operating on or close to schedule with residual delays to trains already enroute following Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 12:03pm
- BetMGM Meadowlands Rail Line
- Trains in and out of PSNY are operating on or close to schedule with residual delays to trains already enroute following Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 12:03pm
- Hudson-Bergen Light Rail
- Trains in and out of PSNY are operating on or close to schedule with residual delays to trains already enroute following Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 12:03pm
- Trains in and out of PSNY are operating on or close to schedule with residual delays to trains already enroute following Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 12:03pm
- Trains in and out of PSNY are operating on or close to schedule with residual delays to trains already enroute following Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 12:03pm
- Northeast Corridor
- Trains in and out of PSNY are operating on or close to schedule with residual delays to trains already enroute following Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 12:03pm
- Trains in and out of PSNY are operating on or close to schedule with residual delays to trains already enroute following Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:34am
- RVL train #5170, the 11:10am PSNY arrival is up to 30 min. late due to Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:28am
- BetMGM Meadowlands Rail Line
- MOBO train #6222, the 10:56am PSNY arrival is up to 40 min. late due to Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:26am
- Northeast Corridor
- NJCL train #3232, the 10:53am PSNY arrival is up to 40 min. late due to Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:01am
- Newark Light Rail
- Trains in and out of PSNY are subject to 20 minute delays due to single tracking as a result of Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:01am
- BetMGM Meadowlands Rail Line
- Trains in and out of PSNY are subject to 20 minute delays due to single tracking as a result of Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:01am
- Hudson-Bergen Light Rail
- Trains in and out of PSNY are subject to 20 minute delays due to single tracking as a result of Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:01am
- Trains in and out of PSNY are subject to 20 minute delays due to single tracking as a result of Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:01am
- Trains in and out of PSNY are subject to 20 minute delays due to single tracking as a result of Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:01am
- Northeast Corridor
- Trains in and out of PSNY are subject to 20 minute delays due to single tracking as a result of Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 11:01am
- Trains in and out of PSNY are subject to 20 minute delays due to single tracking as a result of Amtrak track maintenance in one of the Hudson River Tunnels.
- May 18th, 2018 at 10:02am
- Northeast Corridor
- NJCL train #3227, the 9:48am from Aberdeen-Matawan is up to 15 min. late due to track maintenance.
- May 18th, 2018 at 6:01am
- M&E train #0871, the 5:38am from Hoboken is on the move and up to 20 min. late due to earlier mechanical problems.
- May 18th, 2018 at 5:56am
- M&E train #0871, the 5:38am from Hoboken has not departed due to mechanical problems. An update will follow.