Delays on January 25th, 2017
Latest alerts
- January 25th, 2017 at 7:54pm
- Atlantic City Rail Line
- Update: ACRL train #4634, the 7:06pm from Pennsauken, is now operating up to 45 min. late due to an earlier bridge opening.
- January 25th, 2017 at 7:52pm
- Atlantic City Rail Line
- Update: ACRL train #4639, the 7:33pm from Pennsauken, is now operating up to 25 min. late due to an earlier bridge opening.
- January 25th, 2017 at 7:38pm
- Atlantic City Rail Line
- ACRL train #4639, the 7:33pm from Pennsauken, is up to 10 min. late due to a bridge opening.
- January 25th, 2017 at 7:20pm
- Atlantic City Rail Line
- ACRL train #4634, the 7:06pm from Pennsauken, is delayed due to a bridge opening. Update to follow.
- January 25th, 2017 at 5:49pm
- M&E train #6666 the 5:50pm from Dover is CANCELLED due to a mechanical problem. Customers to train #0858 the 6:20pm from Dover or #6668 the 6:27pm from Dover.
- January 25th, 2017 at 5:13pm
- NEC train #3896, the 5:10pm from Newark Airport, is up to 15 min. late du to earlier police assistance.
- January 25th, 2017 at 5:10pm
- Hudson-Bergen Light Rail
- Update: MBPJ train #1120, the 4:28pm from Ridgewood, is now operating up to 45 min. late due to an earlier mechanical problem.
- January 25th, 2017 at 5:01pm
- Hudson-Bergen Light Rail
- Update: MBPJ train #0051, the 4:48pm from Suffern, is up to 25 min. late due to a train ahead with a mechanical problem.
- January 25th, 2017 at 4:51pm
- UPDATE: M&E train #6641, the 4:18pm from NYPS is now up to 30 min. late due to an earlier mechanical problem.
- January 25th, 2017 at 4:48pm
- Hudson-Bergen Light Rail
- MBPJ train #0051, the 4:48pm from Suffern, is delayed due to a train ahead with a mechanical problem. Update to follow.
- January 25th, 2017 at 4:44pm
- Hudson-Bergen Light Rail
- MBPJ train #1178, the 4:33pm from Ramsey Route 17, is up to 20 min. late due to delayed train #66 ahead.
- January 25th, 2017 at 4:40pm
- Hudson-Bergen Light Rail
- MBPJ train #0066, the 4:23pm from Ramsey Route 17, is up to 20 min. late due to train #1120 ahead with a mechanical issue.
- January 25th, 2017 at 4:38pm
- M&E train #6641, the 4:18pm from NYPS is delayed, due to a mechanical problem. An update will follow.
- January 25th, 2017 at 4:36pm
- Hudson-Bergen Light Rail
- MBPJ train #1120, the 4:15pm from Ramsey, is delayed due to a mechanical issue. Update to follow.
- January 25th, 2017 at 3:14pm
- Atlantic City Rail Line
- ACRL train #4628 the 3:06pm from Egg Harbor is up to 10 min. late due to an earlier mechanical problem.
- January 25th, 2017 at 2:23pm
- NEC train #3850, the 2:11pm from New Brunswick, is up to 15 min. late due to an earlier operational issue.
- January 25th, 2017 at 10:30am
- BetMGM Meadowlands Rail Line
- MOBO Line train #6231 the 10:19am from Bay St. is up to 15 min. late, due to track maintenance.
- January 25th, 2017 at 10:24am
- Northeast Corridor
- NJCL train #3227, the 10:08am from Little Silver is 15 min. late due to track maintenance.
- January 25th, 2017 at 8:27am
- M&E train #6315 the 8:24am from NYPS is CANCELLED due to a mechanical problem. Customers to train #6617 the 8:42am from NYPS making local stops.